Post Contract Strategy
Time, Cost Consultancy through Services
Time, Cost Consultancy through Services
Usually, monthly, following a site visit to ascertain the progress of Works at site, an Interim Valuation is submitted to enable the Engineer to issue the Interim Payment Certificate
The contractual entitlement and cost implications, if any, are determined and recommendations made to the Engineer to enable him to obtain approval from the Client and issue the Engineer’s Instructions.
For sections of Works, where the Client is to nominate a Subcontractor, the Tender documents are prepared and submitted to the Engineer to issue to approved Tenderers. On receipt, a detailed review is carried out and our recommendations are given to the Engineer / Client for final decision and appointment.
The Quantity Surveyor will attend the progress meetings as well as the design team meetings.
On a quarterly basis, a Cost Report is submitted which will clearly indicate
This Report will enable cost control and facilitate any corrective measures required to ensure that the project costs remains within budget.
Assist the Engineer in contractual correspondences to ensure the smooth administration of the Works, as per the signed Contract Documents.
Negotiate and agree the Final Account figure with the Contractor and submit the same to Engineer for issue of Final Valuation Certificate